Browse our publications, press releases and updates from the Kinguélé Aval site.

Publications

18 June 2026

How does a run-of-river dam work?

Francis turbines, penstocks, spillway: how Kinguélé Aval actually works.

Read the article
June 2026

Newsletter #8 — Towards commissioning

Completion of the structures, installation of electromechanical equipment and preparation of commissioning tests.

Read the article
12 May 2026

Kinguélé Aval passes 94% completion

Asonha Énergie reports 94% physical progress on the hydroelectric development.

Read the article
4 April 2026

Meeting the Begnoung eco-guards

Seven eco-guards watch over 1,917.5 hectares of protected forest every day.

Read the article
March 2026

Newsletter #7 — The dam takes shape

A look back at the mass concrete pours and progress on the composite earth-concrete dam.

Read the article
8 February 2026

Visit of the Minister of Energy

A ministerial delegation visited the site to review the progress of the works.

Read the article
15 January 2026

Andock Foula, a village connected to the grid

How electrification changed daily life for the village’s residents.

Read the article
December 2025

Newsletter #6 — Civil works complete

Powerhouse, stilling basin and embankment dam: the main civil works are delivered.

Read the article
3 November 2025

Training tomorrow’s technicians

Skills transfer and training of Gabonese teams in hydroelectric operation.

Read the article
22 October 2025

Biodiversity Action Plan signed

Asonha Énergie and ANPN formalise the creation of the Begnoung Upper Basin Nature Sanctuary.

Read the article
September 2025

Newsletter #5 — The site accelerates

More than 800 people mobilised and civil works ramping up.

Read the article
12 September 2025

Why a composite earth-concrete dam?

One third embankment, two thirds concrete: a design that cuts the carbon footprint by 23%.

Read the article
7 July 2025

A nursery serving the forest

How the revegetation nursery prepares the restoration of natural habitats.

Read the article
June 2025

Newsletter #4 — Focus on equipment

First penstock shells received and preparation for assembling the generating units.

Read the article
14 June 2025

Power purchase agreement confirmed

The electricity produced will supply the Libreville Interconnected Grid for 30 years.

Read the article
20 May 2025

The spillway, guardian of the dam

PK Weir design: up to 700 m³/s discharged, equivalent to a 50-year flood.

Read the article
March 2025

Newsletter #3 — The stilling basin

A close look at the stilling basin and the hydraulic safety of the structure.

Read the article
3 March 2025

Asonha Énergie strengthens its local teams

Recruiting and training Gabonese technicians ahead of the operation phase.

Read the article
14 February 2025

Daily life on site

Meeting the 800 people building the development in the heart of the forest.

Read the article
December 2024

Newsletter #2 — Phase II diversion

The river is successfully diverted, clearing the way for mass concrete pours.

Read the article
19 November 2024

Phase II diversion completed

A major technical milestone on the Mbei River, clearing the way for concrete pours.

Read the article
9 October 2024

Penstocks, the arteries of the powerhouse

Three 3.5 m pipes, each made of about a hundred welded steel shells.

Read the article
June 2024

Newsletter #1 — The diversion channels

Building the two temporary channels, future home of the bottom outlet.

Read the article
February 2024

Special issue — One year on site

A photo review of twelve months of works on the Mbei River.

Read the article
2 October 2023

First debt drawdown

Following financial close in August 2023, the first drawdown launches the financing.

Read the article
22 August 2023

Financial close of Kinguélé Aval

IFC, AfDB, EAIF and DBSA finalise the financing of Gabon’s first PPP dam.

Read the article
8 December 2021

Official start of works

Contractor Sinohydro begins construction of the hydroelectric development.

Read the article