Asonha Énergie
The company

Our history & purpose

From the first pre-feasibility study to commissioning, more than three decades have shaped the Kinguélé Aval project.

A story spanning over 30 years

  1. 1988

    Pre-feasibility study of Kinguélé Aval at 40 MW.

  2. 2005

    Interest study of Kinguélé Aval at 27 MW, as part of the hydroelectric development plan.

  3. 2016

    Formation of the SEEG-Meridiam-FGIS consortium and preliminary studies.

  4. 2017

    Memorandum of understanding signed with the Government; environmental and social impact studies begin.

  5. 2018

    Tender launched for the construction of the development.

  6. 2019

    Environmental certificate obtained; on 24 October, public-private partnership contracts signed with the Gabonese State.

  7. 2020

    Publication of the ESIA, Biodiversity Action Plan and Livelihood Restoration Plan; turnkey EPC contract signed with Sinohydro Corporation.

  8. 2021

    Financing agreements signed with IFC, AfDB, EAIF and DBSA; on 8 December, works begin.

  9. 2023

    Financial close (22 August) and first debt drawdown (2 October).

  10. 2024

    Works reach a sustained pace with construction of the diversion channels – which will become the bottom outlet –, the phase II diversion and the start of mass concreting.

  11. 2025

    Works accelerate with the main civil-engineering structures (concrete dam, earth dam, powerhouse, dissipation basin, etc.).

  12. 2026

    Towards commissioning, with most structures completed and the installation of the hydraulic and electromechanical equipment.

  13. 2027

    Commissioning and operation of the development.